Six years later, dredging’s first phase finally done

By on March 1, 2011

(Town of Southern Shores photo)

Some six years after planning first started, the initial phase of canal dredging is finally finished in Southern Shores.

Dredging of 2.5 miles was wrapped up a little after noon on Friday.

Tom Bennett, the project manager, said in a town statement that about 18,000 cubic yards of material were pumped out and 40 million gallons of water were treated successfully before being returned to the canal system.

“This is the largest project ever undertaken by our town,” Bennett said. “It involved the construction of two large settlement basins with a combined capacity of 5 million gallons of water.”

Delays early in the project revolved around negotiations to find land for settlement basins to treat water from the canals.

After the town cleared that hurdle, dredging got under way. But the project was brought to a halt early in 2010 because the company hired to do the work was unable to extract fine particles from the water before putting it back into the canals.

Bennett called the project “very complex, including the permit process, the required dredging methodology, and the stringent water quality limits required for discharge after the separation of solids.”

All told, the first phase of the canal dredging was budgeted at about $2.2 million, but Town Manager Peter Rascoe said Monday he expected that it would come in at $30,000 under that.

Byrd Brothers Emergency Services of Wilson had taken responsibility over the dredging operations. Byrd sub-contracted with ADI Marine of Minot, N.D., to do the dredging, and ADI Marine contracted with WaterSolve of Grand Rapids, Mich., to perform the water-spoil separation process.

The town will now pursue new permits for the rest of the 7.5-mile canal system and consider funding options, Rascoe said. He said it is not known yet if the rest of the system would be done all at once or in phases.

GO TO HOME PAGE »



ADVERTISEMENT FOR BIDS
Dare County Animal Shelter

Sealed bids for completion of the Dare County Animal Shelter will be received on February 11, 2020, in Dare County Administration Building, 954 Marshall C. Collins Drive, Manteo, NC, for 01-Fencing, 03- Concrete, 04-Masonry, 05-Metals/ Steel, 06-Casework, 07-Roofing, 07-Caulking, 08-Glass and Glazing, 08-Doors, Frames and Hardware, 08-Overhead Doors, 09-Drywall, 09-Flooring, 09-Painting, 10- Specialties, 12- Furnishings, 21-Fire Protection, 23-Mechanical & Plumbing, 26-Electrical, 31-Sitework and 32-Landscaping.

This project will be bid and awarded in accordance with North Carolina law. Sealed proposals from Contractors will be received until 1:00 p.m. All bidders must submit for prequalification by 2:00pm on 1/24/2020. Bids submitted by non-prequalified bidders will not be considered. All bids will be opened and read aloud starting at 2:00 p.m. of the bid day. Bids must be delivered in person and on the supplied Bid Form and include a bid deposit worth 5% of the total bid value. Electronic and faxed bids will NOT be accepted or reviewed. All times are local prevailing times.

Information requests concerning the project shall be submitted in writing to: Alex Palagyi of The Whiting-Turner Contracting Company via email (alex.palagyi@whiting-turner.com)

Bidding material, prequalification material, and complete plans and specifications may be obtained from theWhiting-Turner Building Connected site and will be available until the bid due date. All subcontractors are responsible for emailing Alex Palagyi (alex.palagyi@ whiting-turner.com) for access to the Building Connected site.

The Whiting-Turner Contracting Company and Dare County reserve the right to reject any and all bids, waive informalities and irregularities in bidding, and to accept bids which are considered to be in the best interest of the County. The Whiting Turner Contracting Company and Dare County also reserve the right to require any bidder to submit information needed to determine if said bidder is responsible within the meaning of N.C. Gen. Stat. 143-129.


 


Recent posts in this category

Recent posts in this category

Comments are closed.