The painting of KDH’s logo on the new water tower is underway

By on November 21, 2019

Town of Kill Devil Hills

With the foundation complete and all the steel assemblies set in place and welding complete, the “ball” is temporarily in low position for easier painting. Painting of sphere continues with the painting of logos on sphere.

Raising of sphere into its permanent position was delayed due to weather; could possibly happen after Thanksgiving.

Replacement of the 55-year old, 200,000 gallon elevated water tank at the Fire Station with a 160′ high, 400,000 gallon pedesphere style elevated tank, will almost double its current capacity.

Started on January 10, 2019 the finish date is scheduled for March 4, 2020. The contractor is Landmark Structures, Inc. with a projected cost of $2,855,000.