Nags Head beach project to start mid-July

By on June 28, 2022

(Town of Nags Head)

On June 28, the Town of Nags Head released this update on the summer beach nourishment project that will extend from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16 south to Nags Head’s corporate limits abutting Cape Hatteras National Seashore near Mile Post 21.

Project construction is now expected to take place from July 13 through early September 2022. Equipment mobilization is underway and de-mobilization is expected to take place in September. It is likely the schedule will change over the course of the project.

Oceanfront properties and public beach accesses along South Virginia Dare Trail will not be impacted by the work.

A construction progress map will be updated daily during the project to provide the latest beach closure information.


For updates on 2022 Dare County Beach Nourishment projects visit More Beach To Love.

 

 

 