Dare Schools provide update on FFES and FFMS cleanup

By on August 19, 2023

On Aug. 19, the Dare County Schools issued this update on the “mold mitigation and air quality restoration and air quality control restoration efforts at First Flight Elementary School (FFES) and First Flight Middle School (FFMS) campuses.”

During an emergency meeting of the Dare County Board of Education on Aug. 16, the board, at Superintendent Steve Basnight’s request, approved spending about $933,000 to hire a company, Builder Services, to immediately address humidity control and mold cleanup problems created by inoperable boilers in the two schools. This phase of the work is expected to be completed by the start of school on Aug. 28.

Here is the Aug. 19 information.

After conducting a thorough inspection of both school buildings Thursday, Aug. 18, Builder Services developed an equipment location map and began installing and running dehumidification equipment. This ongoing effort has vastly improved the measured humidity levels throughout both schools. Once humidity levels were properly maintained, crew members began meticulously cleaning air ducts and returns using HEPA-vacuums, as well as furniture. Air-scrubbers were also strategically positioned throughout the buildings to purify the air.

An industrial hygienist who specializes in air quality testing, collected samples across the buildings Thursday that were sent off for analysis. Dare County Schools is currently awaiting those results. During this time, maintenance staff from Dare County Schools began washing coils in HVAC units, replacing ceiling tiles, and cleaning HVAC vents and returns within gymnasium ceilings.

The Incident Response Team convened Friday at noon to review Builder Services progress report and will continue to receive status updates during virtual meetings held Sunday, Aug. 20 and Monday, Aug. 21. Dare County Schools will provide further updates following Monday’s meeting.

 


ADVERTISEMENT FOR BID:

Barnhill Contracting Company will receive sealed proposals for Manns Harbor – EMS/Fire Facility (EMS-8), Kitty Hawk – EMS/Fire Facility (EMS-9), Manteo – Youth Center on January 09, 2024. Times to be given on via addendum #01. See the following SCOPE OF WORK: BP 100 – General Trades, BP 105 – Final Cleaning, BP 205 – Demolition, BP 390 – Turnkey Concrete, BP 400 – Turnkey Masonry, BP 500 – Turnkey Structural Steel & Misc. Steel, BP 505 – Light Gauge Metal Trusses, BP 740 – Roofing, BP750 – Siding, BP 790 – Caulking/Sealants, BP 800 – Turnkey Doors/Frames/Hardware/Toilet Specialties/Accessories/Division 10, BP 840 – Curtainwall/Storefront/Glass/Glazing, BP 925 – Drywall/Framing, BP 960 – Resilient Flooring/Carpet/Base/Epoxy, BP 980 – Acoustical Ceilings, BP 990 – Painting and Wall Coverings, BP 1230 – Finish Carpentry and Casework, BP 1250 – Window Treatments, BP 2100 – Fire Protection, BP 2200 – Plumbing, BP 2300 – HVAC, BP 2600 – Electrical, BP 3100 – Earthwork/Turnkey Site, BP 3213- Site Concrete, BP 3290 – Landscaping. Scopes of work may be added and/or deleted at the discretion of the Construction Manager.

Bid Location and Time: Bid opening will be held in the Barnhill Contracting Rocky Mount Training & GPS Technology Room: 800 Tiffany Bvld, Rocky Mount, NC 27804. Time is as follows: January 09, 2024 at 10:00am and 2:00pm. Times per packages to be given on via addendum #01.

Barnhill Contracting Company will receive, open, and read publicly all bids received in person in the Training & GPS Technology Room at the main office and listed with the virtual viewing at the link to be posted on Barnhill’s Plan Room.

Bids will not be accepted from bidders that are not pre-qualified. No facsimile or email submissions are permitted. Sealed bids are to be hand delivered to the bid opening location noted above or mailed Sealed Bids can be delivered before 9:00am the day of the bid to the Barnhill Contracting Company Office at 800 Tiffany Blvd., Suite 200 Rocky Mount, NC 27804. Attention “Clint Hardison.”

The pre-bid meeting will be held in Person & Zoom Meeting on December 06, 2023 at 10:00 am at the Barnhill Contracting’s Rocky Mount Main Conference Room: 800 Tiffany Bvld, Rocky Mount, NC 27804.

The pre-bid meeting link can be located on Barnhill’s online Building Division Plan Room ( https://app.buildingconnected.com/public/54da832ce3edb5050017438b) and below. A preferred brand alternates meeting will be held via the same link at the end of the Prebid meeting.

Bid Documents can be viewed or downloaded through Barnhill’s online Building Division Plan Room (https://app.buildingconnected.com/public/54da832ce3edb5050017438b) after 12/04/2023.

All Bidders are strongly encouraged to include opportunities for HUB participation wherever possible in their respective Bid submission.  HUB participation is a part of this contract and must comply with all requirements set forth in the Bid Documents.

The Construction Manager and Owner reserve the right to add pre-qualified bidders. The Construction Manager and Owner reserve the right to reject any and all bids. Should you require additional direction, please call Barnhill Contracting Company, (Clint Hardison – 252-802-0740).

Clint Hardison is inviting you to a scheduled Zoom meeting.

Topic: Dare EMS – Phase 2 Pre-Bid Conference

Time: Dec 6, 2023 10:00 AM Eastern Time (US and Canada)

Join Zoom Meeting

https://barnhillcontracting.zoom.us/j/82390692985

Meeting ID: 823 9069 2985

One tap mobile

+17866351003,,82390692985# US (Miami)

+13126266799,,82390692985# US (Chicago)

Dial by your location

  • +1 786 635 1003 US (Miami)
  • +1 312 626 6799 US (Chicago)
  • +1 470 250 9358 US (Atlanta)
  • +1 646 518 9805 US (New York)
  • +1 346 248 7799 US (Houston)
  • +1 213 338 8477 US (Los Angeles)

Meeting ID: 823 9069 2985

Find your local number: https://barnhillcontracting.zoom.us/u/kbYOel03V

Join by SIP

Join by H.323

  • 162.255.37.11 (US West)
  • 162.255.36.11 (US East)

Meeting ID: 823 9069 2985


 

 



Comments

  • charlie

    and the missing boiler parts were part of the original contract for the boilers?.. How long have they been on back order?…if a contractor failed to fulfill his contract why would the school district assume the costs for remediation?…

    Sunday, Aug 20 @ 7:36 am
  • Larry

    It seems odd that NC school systems got COVID money to upgrade / replace HVAC systems specifically to address filtration problems . Wonder where that money went … FYI the mold had be identified and cleaned previously.

    Monday, Aug 21 @ 8:29 am