NCDOT says Colington Rd. project is 75% complete

By on August 22, 2023

Work expected to end in late fall 2023

(File photo: Mark Jurkowitz)

There is a light at the end of the tunnel for the $20 million Colington Road project that began in late January 2022, and is on track to be finished late this fall, according to the North Carolina Department of Transportation (NCDOT).

In an Aug. 22 email sent in response to a Voice inquiry, NCDOT Communications Officer Tim Hass wrote that after consulting with the lead engineer, “the project is currently 75% complete.”

Describing the current status of the work, Hass stated that “The asphalt widening for the bike path has been completed from Colington Harbor to Baum Bay Drive. The contractor is currently cutting ditches and replacing the concrete driveways through this portion of the project, as well as other punch list items, before placing the final lift of asphalt.”

“The contractor will focus on the widening from Baum Bay Drive to Bermuda Bay Blvd. next month,” he added, “before completing the intersection of Colington Road and US 158 later this fall.

The facelift for the winding 4.3-mile-long road—which includes resurfacing; paved shoulders to accommodate bicyclists and pedestrians; realignment of several substandard curves; additional turn lanes; and raising the grade on flood-prone sections—had initially engendered opposition from businesses and residents and saw its share of delays.

For those who travel on the busy road, the construction has been marked by continuous lane restrictions and frequent traffic stops, sometimes as many as three along the stretch from U.S. 158 to Colington Harbour. (There is an old saying that news is something that happens “to or near an editor.” Thus, I acknowledge that these traffic stops have been part of my daily life for a good part of two years.)


ADVERTISEMENT FOR BID:

Barnhill Contracting Company will receive sealed proposals for Manns Harbor – EMS/Fire Facility (EMS-8), Kitty Hawk – EMS/Fire Facility (EMS-9), Manteo – Youth Center on January 09, 2024. Times to be given on via addendum #01. See the following SCOPE OF WORK: BP 100 – General Trades, BP 105 – Final Cleaning, BP 205 – Demolition, BP 390 – Turnkey Concrete, BP 400 – Turnkey Masonry, BP 500 – Turnkey Structural Steel & Misc. Steel, BP 505 – Light Gauge Metal Trusses, BP 740 – Roofing, BP750 – Siding, BP 790 – Caulking/Sealants, BP 800 – Turnkey Doors/Frames/Hardware/Toilet Specialties/Accessories/Division 10, BP 840 – Curtainwall/Storefront/Glass/Glazing, BP 925 – Drywall/Framing, BP 960 – Resilient Flooring/Carpet/Base/Epoxy, BP 980 – Acoustical Ceilings, BP 990 – Painting and Wall Coverings, BP 1230 – Finish Carpentry and Casework, BP 1250 – Window Treatments, BP 2100 – Fire Protection, BP 2200 – Plumbing, BP 2300 – HVAC, BP 2600 – Electrical, BP 3100 – Earthwork/Turnkey Site, BP 3213- Site Concrete, BP 3290 – Landscaping. Scopes of work may be added and/or deleted at the discretion of the Construction Manager.

Bid Location and Time: Bid opening will be held in the Barnhill Contracting Rocky Mount Training & GPS Technology Room: 800 Tiffany Bvld, Rocky Mount, NC 27804. Time is as follows: January 09, 2024 at 10:00am and 2:00pm. Times per packages to be given on via addendum #01.

Barnhill Contracting Company will receive, open, and read publicly all bids received in person in the Training & GPS Technology Room at the main office and listed with the virtual viewing at the link to be posted on Barnhill’s Plan Room.

Bids will not be accepted from bidders that are not pre-qualified. No facsimile or email submissions are permitted. Sealed bids are to be hand delivered to the bid opening location noted above or mailed Sealed Bids can be delivered before 9:00am the day of the bid to the Barnhill Contracting Company Office at 800 Tiffany Blvd., Suite 200 Rocky Mount, NC 27804. Attention “Clint Hardison.”

The pre-bid meeting will be held in Person & Zoom Meeting on December 06, 2023 at 10:00 am at the Barnhill Contracting’s Rocky Mount Main Conference Room: 800 Tiffany Bvld, Rocky Mount, NC 27804.

The pre-bid meeting link can be located on Barnhill’s online Building Division Plan Room ( https://app.buildingconnected.com/public/54da832ce3edb5050017438b) and below. A preferred brand alternates meeting will be held via the same link at the end of the Prebid meeting.

Bid Documents can be viewed or downloaded through Barnhill’s online Building Division Plan Room (https://app.buildingconnected.com/public/54da832ce3edb5050017438b) after 12/04/2023.

All Bidders are strongly encouraged to include opportunities for HUB participation wherever possible in their respective Bid submission.  HUB participation is a part of this contract and must comply with all requirements set forth in the Bid Documents.

The Construction Manager and Owner reserve the right to add pre-qualified bidders. The Construction Manager and Owner reserve the right to reject any and all bids. Should you require additional direction, please call Barnhill Contracting Company, (Clint Hardison – 252-802-0740).

Clint Hardison is inviting you to a scheduled Zoom meeting.

Topic: Dare EMS – Phase 2 Pre-Bid Conference

Time: Dec 6, 2023 10:00 AM Eastern Time (US and Canada)

Join Zoom Meeting

https://barnhillcontracting.zoom.us/j/82390692985

Meeting ID: 823 9069 2985

One tap mobile

+17866351003,,82390692985# US (Miami)

+13126266799,,82390692985# US (Chicago)

Dial by your location

  • +1 786 635 1003 US (Miami)
  • +1 312 626 6799 US (Chicago)
  • +1 470 250 9358 US (Atlanta)
  • +1 646 518 9805 US (New York)
  • +1 346 248 7799 US (Houston)
  • +1 213 338 8477 US (Los Angeles)

Meeting ID: 823 9069 2985

Find your local number: https://barnhillcontracting.zoom.us/u/kbYOel03V

Join by SIP

Join by H.323

  • 162.255.37.11 (US West)
  • 162.255.36.11 (US East)

Meeting ID: 823 9069 2985


 

 



Comments

  • Jay

    As a Colington resident this update is good news. The road improvements are long overdue.
    Yes waiting in the M-F lane closures is getting tiresome. Fred Smith employees are doing a good job maintain the traffic flow. I’m curious to see how the new new drainage ditches flow i.e. work. Will NCDOT maintain these ditches to keep them flowing?

    I have noticed some drivers cannot stay in their lane. They are drifting across the right white line and partially driving in the pedestrian/bike lanes.

    Mark thanks for the update!

    Wednesday, Aug 23 @ 7:23 am
  • WindyBill

    Well Jay, Of course you are right. Has always been and will always be. Here’s a driving game I enjoy on Colington Road. It does compell attention to the road ahead. Count the number of times the car ahead has a tire touch or go more than halfway over the yellow or white lines (your call). Guesses on the average? Completely over 3 times may merit a 911 call. Challenge: A precise driver can drive the full length of the road at the speed limit, without touching the: brakes (traffic permitting), white or yellow lines, or squeeling tires. Can you?

    Wednesday, Aug 23 @ 10:36 am
  • Mark Jurkowitz | Outer Banks Voice

    Windy, here’s what I wish I had done once they started with the traffic stops. Keep a running tally on how many times I got to keep going and how many times I had to stop. I’m sure this is an exaggeration, but I swear I’ve hit the red light about 75% of the time.

    Wednesday, Aug 23 @ 1:07 pm
  • BKT

    Nice progress
    Great location to live and play
    When the news paper company developed the property, they could have never imagined needing this kind of road. Wish our government leaders and developers would look a little further in the future when designing this large of a development.

    Wednesday, Aug 23 @ 2:13 pm
  • Luminous

    Something’s off here trying to reconcile “75% done” and “expected to be finished this fall.” They’ve been at this for the better part of two years. If it’s only 75% done, that may suggest they’re behind schedule. Or when they say “75% done,” do they mean they have a checklist of objectives, many of which are quick to do but only get checked off near the end?

    The annoying part to me recently is that early in the project, the one-lane sections were short, and they were working there. That keeps the waiting backups and delays to motorists briefer than what I’ve seen all too often lately which are extended sections of roadway blocked while they’re only working on a relatively small section of it. With a long section of roadway blocked one-way, it takes increasingly longer for backed-up traffic to clear it, which leads to more delays. It seems like convenience to the contractor in not having to move cones and gates is taking priority over convenience to the motorists. This is also a public safety issue for emergency responders.

    Wednesday, Aug 23 @ 4:08 pm
  • Jay

    Windy I can travel Colington Road at 35 and stay in my lane. My full size crew cab truck needs to take the curve at Billy’s a little slower.

    My point on drivers crossing the white line was to alert pedestrians and bikers not to get over confident thinking those left side bike lanes are safe to travel without staying alert.

    Wednesday, Aug 23 @ 5:23 pm
  • WindyBill

    Jay: Cool!

    Wednesday, Aug 23 @ 8:16 pm