By Mark Jurkowitz | Outer Banks Voice on April 8, 2026
The Currituck County Commissioners did not hear encouraging news during an update on the status of the Mid-Currituck Bridge project from NCDOT officials on Monday, April 6.
“The project, unfortunately, is not financially feasible without additional funding,” NCDOT deputy director for planning and programming David Wasserman told the commissioners at their April 6 work session. That message was also delivered at a recent Albemarle Rural Planning Organization (ARPO) meeting.The Outer Banks Voice – Increasing costs may doom Mid-Currituck Bridge project
The problem, as laid out in the presentation from Wasserman, boils down to a funding gap of that is about $1 billion on a project now estimated to cost about $1.2 billion. By way of comparison, according to the presentation, when the bridge project was evaluated in 2014, the estimated price tag was $411 million, with the funding coming from $238 million in tolling revenue and $173 million allocated by the state.
What happens next is in the hands of ARPO, which meets on April 15 and faces two choices outlined by Wasserman. The Outer Banks Voice – Fate of Mid-Currituck Bridge hangs on April vote
One option would be to choose a “status quo” plan with no changes as NCDOT continues to look for alternative funding such as grants and the $173 million in state funding remains for the project.
The other option is to allow the project to go back into the State Transportation Improvement Program (STIP) ranking system, which would mean competing again for funding in a challenging environment that favors more urbanized areas. In addition, the $173 million in funding would become available for other projects in Division I, which includes 14 counties in Northeastern North Carolina.
At the meeting, Currituck Commissioners—who peppered Wasserman with questions and concerns—expressed pessimism about the future of the bridge. One of those who clearly voiced frustration was State Senator Bobby Hanig, who attended the work session.
Noting that the funding process seemed weighted against smaller rural counties, Hanig said that “until we start funding rural areas more…we’re never going to change,” adding that in this system, “we’ll remain at the bottom of the totem pole.”
Wasserman responded by acknowledging that “the issue is there is not enough funding for transportation overall.”
While the NCDOT calculations put the bridge project’s tolling net cash flow at about $200 million, several commissioners raised the idea of increasing the tolls to a level considerably higher than the $35-$40 that has been suggested.
David Roy, the director of innovative finance at the North Carolina Turnpike Authority who joined the session remotely, said that although toll rates “could be a little higher…the higher the rate, the more people are going to choose an alternative route.” He also said that when forecasting project revenues, states officials “don’t look to set the tolls at the absolutely maximum rate.”
Summing up the general prognosis for the bridge and the mood of the moment, Wasserman told the commissioners that “at the end of the day, the funding will still remain a challenge for this project.” But, he said, “no one’s suggesting to walk away from this project.”
Comments
Hack This
This is a tourisim related project. Period. Use that [selfish] rental tax revenue. Or, even better, stop renting the houses and building the envitomentally destructive McMansions.
Ed
Have these guys do it, they did the whole alligator river bridge replacement for a third of that: https://www.enr.com/articles/60137-skanska-tapped-for-450m-bridge-replacement-on-north-carolina-coast
Tolls
The problem with relying on tolls is that it’s not cash on hand to pay for materials or labor to build the bridge. Who wants to take a loan for a two lane bridge to nowhere for $1,200,000,000.00?
Traffic lights and lighted cross walks in Duck and Southern Shores will help mitigate traffic flow congestion for a fraction of what it costs to build a bridge that will costs $100-200 to go one way.
Rick
We might as well put this baby to bed. It’s over. This project is not happening. It’s been talked about for what, 50 years now? And it keeps getting more expensive. They’re talking about $30-40 tolls, and I knew this project jumped the shark and would never happen when one of the county commissioners talked about how they thought people would happily pay 3 or 4 times more than the proposed rate. Nope, sorry. Someone is completely out of touch here, and I don’t think it’s me. The Chesapeake Bay bridge tunnel is one of the most expensive water crossings on the planet, at what, $18? This bridge would be maybe a third of that size/distance with no tunnels, but you want to charge 2 or 3x that amount?! Any elected official that thinks people will pay triple digit dollar amounts to drive over a bridge that saves them an hour or so must be smoking a whole lot of crack. Just kill this project already. It’s getting so expensive that no one would ever use it anyway with the ridiculous tolls. I’ve read countless comments on these articles in this website that offer better solutions to the actual problems, and they’re all cheaper and more sensible than this bridge.
Too Late..
No Eco- System needs this anyway! Certainly not in the OBX!
Currituck missed the mark on applying for grant money and are now back-pedaling talking about the cost of the toll$. C’mon! Really?
North Carolina has other places that can use that grant$ for now!
Doesn’t make sense anymore!
Stop $elling + Paving Paradise to the hilt dummies!
profbraddock
Stick a fork in it, it’s done. And stop building more houses/multiuse structures in Corolla.
Jay
Thank God hopefully it’s about over so all parties will be forced to implement alternative , cheaper and honestly much more realistic solutions. Of course that will be on duck mostly so we’ll have to wait until they’ve had enough and are willing to adjust somethings in their lil town.
Greg
The bottom line is that the access to Corolla should have been taken care of prior to the complete development of that area. Why were development permits issued with such convoluted access that would it’s way through the communities in Northern Dare County. The State regulators who blessed the rampant development jumped the gun. Now there is a mess. The mess needs to be cleaned up. Build the Bridge.
Jay
I don’t like the idea of tolls. If money is needed add tolls to the WMB, Manns Harbor Bridge, and Virginia Dare Memorial Bridge. Use the various EZ Passes to collect the tolls. Reduced rates for residents and sock it to the visitors. Paradise has been long gone. Brace yourselves for another new Shell gas station going in between Wawa and Circle K on the bypass in KDH.
MCB RIP
Agree many out of touch can’t imagine residents or essential workers paying $30-40 to cross a 2-lane bridge so it seems a seasonal investment for others yet impacts Corolla.
Maybe spend the $ on managing the multiple crosswalks in SS- FIX Duck with pedestrian vehicle management and either require bicycles to use the path north of main area or widen 12 for bike lane and turn lanes connecting to Sanderling.
Oh and turn lanes along the Corolla Ocean Sands strip of Rt12.
These approaches could benefit everyone. year round
Craig
Pedestrian overpasses in Duck. Much cheaper.
Dom Bostich
When one embarks on a project based on a dupe (“It is necessary for rapid evacuation”) and greed, said project will likely wither on the vine. Granted, this vine seems to have nine lives but–guess what…it will only increase in price, NC has LOTS of more critical growth areas worthy of highway funds, and the area is not mass-appeal enough for federal pols to get involved.
This ain’t the North Jersey shore or Delaware coastline, where you have MANY major movers and shakers exerting influence at a state and federal level. This is Corolla and Duck…built out, overdeveloped, mishandled and small potatoes.
In essence, y’all outpriced yourselves.
When Gordon Gekko said: “Greed is good” he wasn’t speaking in absolutes.