By Kip Tabb | Outer Banks Voice on August 13, 2026
Update: On Thursday, Aug. 13, a day after some residents criticized Currituck’s beach management process, the Corolla Civic Association (CCA) posted this beach nourishment presentation delivered by Dare County Manager Bobby Outten at a CCA meeting on July 22. Facebook The presentation reviews the basics and history of beach nourishment projects in Dare County, ranging from financing to results.
At an Aug. 12 meeting on Currituck County’s beach nourishment plan, those in attendance voiced frustration with the process and questioned whether the county was committed to protecting homes, property and the beach along the Currituck Banks.
“I can see this turning into another joke, just like the Mid-Currituck Bridge,” said one. “They’re going to start losing houses while we’re analyzing and struggling over what to do.”
“Has there been a basic decision that the county is going to do something, or is this a cynical window dressing?” asked another.
The meeting at the Outer Banks Center for Wildlife Education in Corolla was moderated by Coastal Protection Engineering (CPE) Senior Project Manager Ken Willson. Attended by Corolla and Carova residents, it focused on the 2025 Beach Management Plan presented by Willson in May. The plan is the sixth annual beach assessment report. The Outer Banks Voice – At Corolla meeting, CPE Engineer outlines options for addressing beach erosion
The 2025 draft report recommended beach nourishment for approximately two miles of beach south of the horse gate in Corolla.
One meeting attendee asked Currituck County Manager Rebecca Gay to “pass along to the commissioners that Corolla feels neglected. It’s like the county doesn’t care about us.” Willson pushed back on that idea, explaining that the county’s process for monitoring and assessing the beach over a number of years is standard procedure.
“Ultimately this isn’t a unique process to have these discussions and to have tension politically trying to figure out what the best division of who should pay for this and how the cost is spread,” he said. “That is the most complicated and difficult part of these projects.”
Residents at the meeting were particularly critical of the county’s use of occupancy tax revenues to pay for police and emergency services, a practice that is typically not an allowed use of occupancy taxes in the state. On May 22, however, the North Carolina Supreme Court ruled in favor of Currituck County, finding that the occupancy tax language did not prohibit it from spending funds on public safety.
Some North Carolina’s beach counties that have been permitted to levy an occupancy tax, dedicate a portion of that tax to beach nourishment, attendees noted. Dare County sets aside two percent of occupancy tax revenues for beach nourishment projects.
Pressed on the point, County Manager Gay said that “Our special legislation allows the…commissioners to spend tourism-related dollars on beach nourishment.” But the county does not have a dedicated amount set aside for nourishment projects.
Members also criticized statements from county commissioners representing mainland Currituck. “It is distressing that we keep hearing commissioners saying that nobody on the mainland will ever pay a penny towards this, even though they reap the benefits,” one of them asserted.
Corolla resident Tony Cerri noted that Currituck Commissioner Chairman Paul O’Neal has invited him to brief him on the subject on Sept. 29, adding that “at least the commissioners have said, ‘Come talk and open that dialogue.’”
During the Aug. 12 meeting, the issue arose about whether a beach service district that would allow the county to assess an additional property tax on residents in the nourishment areas would be needed.
Asked by the Voice if a service district was being considered, Gay replied, “There will definitely be a service district established if [the commissioners] choose to move forward with nourishment.”
For his part, Willson explained that the expenses for a nourishment project begin before even the first grain of sand is pumped onto the beach.
“There will be somewhere between half a million and a million, maybe a little bit more spent on permitting the project, designing the project, making sure that you’ve got all of the sand that’s going to be pumped onto the beach verified as compatible,” he said, adding that this phase of the project typically takes “a couple of years.”
“There isn’t a beach nourishment until the county says we’re ready to move forward,” he stated. “If we got the green light today, we’re looking at a beach nourishment project in 2029. Maybe it could happen in 2028, but it seems highly unlikely.”
Comments
Missing Piece
Maybe premature for current discussion but what’ the plan to comply with NC public access mandates?
Any public funds used for beach nourishment requires public access including walkways and parking.
Are the HOA and gated communities aware and have a timeline to complete any necessary infrastructure?
SMH
You build on shifting sands You destroy the fragile eco system of barrier Island You rake in thousands of dollars And the tax payers should fit the bill. The profits made by investors should be covering the costs!!!
Craig
Your cash cow is expensive to maintain.
Hack This
Missing Piece or MISinformation. Noone has to comply with anything. Ever.
North Carolina does not have a single statewide mandate guaranteeing public access points or regulating all beaches uniformly. Instead, wet sand areas below the high tide mark are state-owned for public use. Period.