Recent NC 12 closure impacted work at Buxton groin repair site

By on November 1, 2026

(Dare County photo)

On Oct. 31, Dare County provided this update on the ongoing Buxton groin repair project.

Work on the Buxton terminal groin repair project continues to move forward, with 2,718.03 tons of armor stone now stockpiled on site. Crews have continued debris removal and site preparation as weather and conditions have allowed, despite a temporary interruption in rock deliveries last week due to impacts from the coastal storm that caused the closure of N.C. Highway 12. 

The county’s contractor, SJ Hammill, was scheduled to drive the first sheet pile on Friday, Oct. 30, marking an important step forward in the project. Debris removal and sheet pile installation are expected to continue simultaneously as work progresses. Crews are also working through the weekend to maintain progress, with rock deliveries scheduled to resume on Monday, Nov. 2, weather and site access permitting. Additional updates will be shared at www.DareNC.gov/Projects as further details are made available.  

Back in June, the Dare County Commissioners selected SJ Hammill, which submitted an $8.6 million bid, as the contractor for the project. That contract called for the substantial completion of 450 linear feet out of 640 feet of terminal groin by Dec. 15.

An Oct. 5 Dare County update on the groin repair effort stated that “the contractor is also evaluating whether the delivery restrictions could warrant an extension to the project schedule…County officials have stated that an adjustment to that deadline may be reasonable if the recent delivery delays affect the overall schedule.”

 