Latest update on Buxton beach nourishment and groin repair

By on September 17, 2026

September 15, 2026 – Looking north from the completed southern section, nourishment advances into the remaining project area as Buxton enters the final phase of construction. Dare County - More Beach To Love
previous arrow
next arrow
 
September 15, 2026 – Looking north from the completed southern section, nourishment advances into the remaining project area as Buxton enters the final phase of construction. <br> Dare County - More Beach To Love
September 12, 2026 – Nourishment advances northward after completion of the southern Buxton shoreline. <br> Dare County - More Beach To Love
September 8, 2026 – With two dredges on site, crews push southward, placing and shaping sand as nourishment advances toward completion of the beach berm along Buxton Village. <br>Dare County - More Beach To Love
Construction Progress Map Weather permitting, GLDD expects to complete the project by the end of September 2026. <br> Dare County - More Beach To Love
previous arrow
next arrow

On Thursday, Sept. 17, Dare County released a progress report on the ongoing Buxton beach nourishment project and the work to repair the southernmost groin near the former Cape Hatteras Lighthouse site.

The beach nourishment project has just moved into its final phase, with a completion date in late September. The groin repair is expected to be substantially completed by or before mid-December. Here is the latest information.

Buxton Beach Nourishment

Great Lakes Dredge & Dock Company has announced that the 2026 Buxton beach renourishment project entered its final phase on Wednesday afternoon, (September 16), as the contractor completed renourishment along the developed Village of Buxton shoreline and shifted operations northward into the Cape Hatteras National Seashore.

To date, approximately 1.5 million cubic yards of sand—75% of the 2.0-million-cubic-yard total—has been placed on the beach within the project area.  

Click here to view the 2026 Buxton beach nourishment project progress map. 

With the protective dune and berm in Buxton complete, the remainder of construction activities will consist of widening the beach along a portion of the Cape Hatteras National Seashore. Weather permitting, Great Lakes Dredge & Dock remains on track to complete nourishment by the end of September 2026.

Native dune grasses are scheduled for installation on the newly-constructed dune along Buxton in November.

 

Buxton Terminal Groin Project

Construction is underway on the trestle in preparation for removing the seaward remnants of the former jetty. Following removal of the old material, new sheet piles will be driven and reinforced with armor stone. The project remains on schedule, with substantial completion anticipated by December 15, 2026, or sooner. Additional details will be posted as more information becomes available.

 